Banbury Lane Closures
Please see note from EKFB regarding Banbury Lane Closures.
The next closure of Banbury Lane is planned for 3 to 5 December. If we are unable to go ahead on these dates, the following dates will be required: 8 to 10 December 2025.
There will be NO closure on 15 & 16 December. This work has been rescheduled for early January, as per the dates below.
Duration
Updated 20 November 2025.
- 3 December to 5 December with contingency dates of 8 December to 10 December
- 7 January to 16 January (excluding the weekend)
- 26 January to 4 February (excluding the weekend)
Please note:
- Further dates are expected in spring 2026 as we complete work in the area.
- These dates are subject to change dependent on the construction schedule and weather.
- Updates will be made to this notification online and on the roadside date boards.
We will continue to keep closure durations to a minimum whenever possible and thank you for your continued patience while we complete this work.
Kind regards
Haidee Williams
Engagement Manager G2S